enCore Energy Expects Upper Spring Creek Uranium Permit by November 13

enCore Energy Expects Upper Spring Creek Uranium Permit by November 13

enCore Energy’s Nasdaq shares changed hands at about $0.77 on October 29, according to third-party market data. Two days earlier, the company said the permit it has been chasing since May 2025 now needs only a final signature. The plant that permit would switch on is already built, and its costs are already expensed.

enCore Says Upper Spring Creek Permit Needs Only a Final Signature

enCore Energy Corp. (TSXV: EU) (Nasdaq: EU) disclosed on October 27 that the first Production Area Authorization at its 100%-owned Upper Spring Creek project in South Texas has completed technical review and public notice at the Texas Commission on Environmental Quality (TCEQ). A Production Area Authorization, or PAA, is the state permit that allows in-situ recovery (ISR) extraction within a defined wellfield. ISR recovers uranium by circulating a solution through the ore body underground and pumping it back to the surface, rather than digging the rock out.

Final authorization is expected on or before November 13, 2026. The company called that date an acceleration from the timing in its Q2-2026 guidance.

It took a while. The application went in on May 27, 2025, and moved through seven technical revision cycles and two public notice periods. TCEQ issued an initial draft permit on August 28, 2026 and a final draft on September 23. Public comment closed October 19, with a grace period for postmarked comments that ended October 24.

“Permitting has been the last step between the infrastructure we have built in South Texas and new production,” CEO Richard Little said in the release.

Upper Spring Creek Still Needs a Disposal Well Approval

The PAA is not the only open item. Upper Spring Creek also needs TCEQ operational approval of a waste disposal well that will take the bleed stream from ISR operations. enCore says the well is constructed and in final testing and review. No date was given for that approval.

On the surface sits a satellite ion exchange plant, where dissolved uranium is captured on resin. The loaded resin will be trucked to enCore’s Rosita Central Processing Plant and processed into yellowcake, the dried uranium concentrate sold to utilities. The company describes Upper Spring Creek as the largest satellite facility it has built to date. The release gives no capacity or expected production figure in pounds.

Little told investors the company is ready to begin injection and recovery as soon as the final permit arrives.

Alta Mesa PAA-3 Extension and PAA-8 Remain in TCEQ Review

Two more production areas sit at Alta Mesa, which enCore runs in a joint venture where it holds 70% and Boss Energy Ltd. (ASX: BOE) holds 30%, according to enCore’s second-quarter 10-Q. TCEQ is still working through technical review of the PAA-8 application and the PAA-3 Extension amendment. State rule changes on public notice and hearings that took effect May 1, 2026 mean neither faces a public hearing opportunity, per the company.

The release is not consistent on timing. Its introduction says both are expected before the end of the year. Its highlights put the PAA-3 Extension by year-end and PAA-8 early in the new year. Separately, enCore’s August results release had guided to final permits for Alta Mesa’s Wellfield 8 by the end of Q1-2027.

enCore’s First-Half 2026 Extraction Fell to 131,274 Pounds

For the six months ended June 30, 2026, enCore extracted 131,274 pounds of U3O8, down from 317,613 pounds in the same period of 2025. U3O8 is the standard measure of uranium concentrate. The company still delivered 485,000 pounds into contracts at an average $70.10 per pound, but 360,000 of those pounds were purchased rather than produced. The weighted average cost of delivered pounds came to $75.54, above the average sale price.

Loss per share for the half was $0.19, against $0.16 a year earlier. Total liquidity stood at $88.4 million on June 30, of which $21.8 million was unrestricted cash; marketable securities and inventory made up the rest.

Leadership changed in April. The board replaced CEO Robert Willette with Richard Little and founder William Sheriff returned as executive chair. A workforce reduction followed in July, and Alta Mesa’s Wellfield 7 was scheduled to stop recovery in Q3-2026 as it reached the end of its natural life.

enCore Shares Trade Below $1 Ahead of the Permit Decision

At $0.77, the Nasdaq line sits under Nasdaq’s $1.00 minimum bid price for continued listing. Nasdaq issues a deficiency notice once a stock closes below that level for 30 consecutive business days. No such notice from enCore was identified in the filings and releases reviewed for this article.

The share price figure comes from a third-party data provider, not a company disclosure.

enCore’s Upper Spring Creek Permit Is Due On or Before November 13

enCore expects final TCEQ authorization of Upper Spring Creek PAA-1 on or before November 13, 2026; it has not disclosed a date for the waste disposal well’s operational approval. The company expects the Alta Mesa PAA-3 Extension by the end of 2026, and its release gives PAA-8 as both year-end and early 2027. At Dewey Burdock in South Dakota, which has all necessary federal permits, state permitting began June 15, 2026, and the company anticipates development in 2028 subject to state permits.

Sources

Editorial Disclosure

This article is based entirely on publicly available information, including enCore Energy’s October 27, 2026 PRNewswire release and its SEC filings, along with third-party share price data as of October 29, 2026. The securities discussed are enCore Energy Corp. (TSXV: EU) (Nasdaq: EU) and Boss Energy Ltd. (ASX: BOE), enCore’s 30% joint venture partner at Alta Mesa. aktiego.com has not received any compensation from enCore Energy, Boss Energy, their management, investor relations representatives, or any third party. No staff member or principal of aktiego.com holds a position in either security at the time of publication.

Upper Spring Creek PAA-1 had not been granted as of publication. The November 13, 2026 date is enCore’s own expectation, not a commitment from the TCEQ, and the separate waste disposal well approval needed for optimal operation remains outstanding with no disclosed date. The Alta Mesa PAA-3 Extension and PAA-8 timelines are company-stated, and the October 27 release gives two different expectations for PAA-8. The release discloses no production capacity or volume figure for Upper Spring Creek, and readers should not infer one from this article.

For the six months ended June 30, 2026, enCore’s extraction fell to 131,274 pounds from 317,613 pounds. Of the 485,000 pounds delivered into contracts, 360,000 were purchased; the weighted average cost of delivered pounds exceeded the average sale price. Of $88.4 million in reported total liquidity, $21.8 million was unrestricted cash. No going-concern language was identified in the sources reviewed. The company changed its chief executive in April 2026 and reduced its workforce in July 2026.

The share price cited is sourced to a third-party data provider rather than a company disclosure. enCore’s Nasdaq shares traded below Nasdaq’s $1.00 minimum bid price as of October 29, 2026; no Nasdaq deficiency notice was identified in the filings and releases reviewed. Neither the TSX Venture Exchange nor its Regulation Services Provider accepts responsibility for the adequacy or accuracy of enCore’s press releases, per the company’s own standard disclosure.

Small cap and micro-cap stocks listed on the TSXV, Nasdaq, and ASX, including uranium producers exposed to commodity price swings, are speculative investments carrying significant risk including potential total loss of capital. Coverage on aktiego.com is provided for informational and educational purposes only. aktiego.com is not a registered investment advisor. Nothing in this article constitutes financial, investment, or professional advice. Readers are encouraged to conduct their own due diligence and consult a qualified financial advisor before making any investment decisions. For more information please see our full DISCLAIMER

AktieGo

More Market Insights
on YouTube

Watch our latest market briefings, CEO interviews and stock deep dives covering the companies and sectors we follow.

Nvidia's $500 Billion AI Financing Bet
Nvidia’s $500 BILLION AI Financing Bet: Brilliant Move or Hidden Risk?
The Drone Revolution: Why Warfare Has Changed Forever
The Drone Revolution: Why Warfare Has Changed Forever
The AI CyberSecurity Arms Race Has Begun
The AI CyberSecurity Arms Race Has Begun
Market Briefings
3× per week
Stock Deep Dives
In-depth analysis
CEO Interviews
Exclusive insights
Emerging Sectors
Mining · Tech · Energy · Biotech
The AktieGo Brief

The market moves fast.
Our briefing keeps up.

Curated updates on stock picks, company spotlights, and in-depth market analysis across mining, biotech, energy, crypto, and tech — delivered straight to your inbox. Join thousands of investors who start their morning with the AktieGo Brief.



Name

BRIEF