Fifteen percent of an unbuilt factory in Abu Dhabi now costs US$30 million. Japanese trading house Hanwa and a Japanese government agency paid it. The seller, NextSource Materials, trades at a total market value that data providers put between roughly US$35 million and US$45 million.
NextSource Closes Hanwa-JOGMEC Deal, Keeps 85% of UAE Anode Plant
NextSource Materials Inc. (TSX: NEXT, OTCQB: NSRCF) signed the binding Shareholders’ Agreement with Hanwa Co., Ltd. and the Japan Organization for Metals and Energy Security (JOGMEC) on November 25 and confirmed the cash is in. The pair now hold 15% of NextSource Battery Materials Holding Ltd., the Abu Dhabi plant company. NextSource keeps 85%. CEO Hanré Rossouw called it a move “from agreement to execution.”
The plant will make active anode material, the processed graphite in a lithium-ion battery’s negative electrode. Phase 1 targets about 14,000 tonnes a year, with ramp-up expected in the second half of 2027. Mitsubishi Chemical holds a binding, multi-year offtake. A second offtake is only a letter of intent, with terms undisclosed.
Thirty million does not build it. Phase 1 capital costs were earlier reported at about US$150 million. NextSource is in “advanced discussions” with other strategic investors for a further 35% of the project company and is talking to lenders. Nothing definitive yet.
The parent is stretched. Its MD&A for the year ended June 30, 2026 flags a material uncertainty that may cast significant doubt on its ability to continue as a going concern. Year-end cash was about $11.6 million against a working capital deficit of roughly $25.1 million, mostly Vision Blue borrowings classed as current. Its Molo graphite mine in Madagascar runs in cost-saving campaigns: five in fiscal 2026, 880 tonnes shipped.
Follow-Up: GMG Signs UKBIC Deal to Build Its Graphene Cells in Coventry
Graphene Manufacturing Group Ltd. (TSXV: GMG, OTCQX: GMGMF) signed an initial service agreement on November 19 with the UK Battery Industrialisation Centre (UKBIC), the UK’s national battery manufacturing development facility. GMG makes the battery materials in Brisbane. UKBIC builds and forms the G®CELLS in Coventry, starting with pouch cells. GMG pays for the work and keeps the IP.
What GMG buys is time. It can hold off on its own large-format cell factory until the technology is further de-risked, and get sample cells closer to UK and European prospects. No fees, volumes, first-cell date or customers were disclosed.
Six days later, GMG reported quality progress at a higher production rate at its Gen 2.0 graphene plant. How much higher, and which quality measures, it did not say. Chairman Jack Perkowski said the result “shows that GMG’s proprietary plasma-based process can scale.” Big word for a release with no production figures.
At its July startup, GMG targeted quality and volume optimization by the end of September. The plant, designed for 10 tonnes a year, is still being optimized. The board just approved another A$1.26 million, mostly for its final self-powered generators and batteries plus a new Fulcrum Facility.
Charbone Grows Hydrogen Customers From 3 to 28 as Q3 Gas Income Rises 21%
Charbone Corporation (TSXV: CH, OTCQB: CHHYF) posted Q3 2026 results on November 25. Gas income rose 21% to C$0.55 million. Gas income margin went to about 26% from about 7%. Active customers grew from 3 to 28, and the delivery fleet from 2 units to 11.
Charbone makes ultra-high purity (UHP) hydrogen in Sorel-Tracy, Quebec, where its Phase 1A unit runs on renewable power from Hydro-Québec. Phase 1B needs a few more weeks. The company cited integration of equipment for higher purity specifications and recovery of vented UHP oxygen.
The base is tiny. Cash was C$1.5 million at September 30. Charbone has drawn C$4.5 million of a C$10 million secured convertible loan facility, so dilution is a live risk. Its 2025 MD&A disclosed a material uncertainty that may cast significant doubt on its ability to continue as a going concern.
NextSource, GMG, Charbone: Forward-Looking FAQ
The rest of the capital. Talks with additional strategic investors for a further 35% stake, and with lenders, are ongoing with no definitive agreements announced, and the company itself warns that financing may not arrive on acceptable terms or on schedule.
No. GMG is the paying customer here. The release names no buyers, volumes or start date for UK-made cells.
Integration of equipment for higher purity specifications and recovery of vented UHP oxygen. Charbone hosts a results webinar on December 1 at 11:00 AM ET, though it has not said whether Phase 1B timing will be updated there.
Sources
- NextSource Materials: Completes Shareholders’ Agreement with Japan’s Hanwa and JOGMEC and Receives US$30M Investment for UAE Battery Anode Facility, ACCESS Newswire via Investing News Network, November 25, 2026
- NextSource Materials: Secures Binding Agreement for US$30 Million Strategic Investment from Japan’s Hanwa and JOGMEC, Newswire.com, September 28, 2026
- NextSource Materials: Management’s Discussion and Analysis, year ended June 30, 2026 (SEDAR+ filing)
- Miningmx: NextSource Closes In on Abu Dhabi Plant Funding, May 21, 2026
- Graphene Manufacturing Group: GMG Signs Service Agreement with the UK Battery Industrialisation Centre to Manufacture G(R)CELLS in the United Kingdom, November 19, 2026
- Graphene Manufacturing Group: GMG’s Gen 2.0 Graphene Manufacturing Plant Makes Crucial Quality Progress at New Higher Production Rate, Newsfile via FinancialContent, November 25, 2026
- Graphene Manufacturing Group: GMG Reaches Major Commercial Milestone with On-Time Startup of Second Generation Technology Graphene Production Plant, via pv magazine Australia, July 2026
- Charbone Corporation: CHARBONE Reports Q3 2026 Financial Results with Gas Income and Margin Growth, November 25, 2026
- Charbone Hydrogen Corporation: Management’s Discussion & Analysis, year ended December 31, 2025 (SEDAR+ filing)
- BNN Bloomberg: CHARBONE Reports Strongest Quarter to Date in Preliminary Third-Quarter Results, November 12, 2026
Editorial Disclosure
This roundup is based entirely on publicly available information including press releases, regulatory filings, and third-party market reporting. Securities discussed: NextSource Materials Inc. (TSX: NEXT, OTCQB: NSRCF); Graphene Manufacturing Group Ltd. (TSXV: GMG, OTCQX: GMGMF); Charbone Corporation (TSXV: CH, OTCQB: CHHYF). aktiego.com has not received any compensation from any company mentioned, their management, investor relations representatives, or any third party, and no staff member or principal of aktiego.com holds a position in any security mentioned as of publication.
NextSource: going concern material uncertainty disclosed in its FY2026 MD&A; working capital deficit; further equity and debt financing for the UAE plant not yet secured; second offtake at letter-of-intent stage only.
GMG: UKBIC agreement is a paid service arrangement, not a supply or offtake contract; no financial terms, volumes or timeline disclosed. Gen 2.0 quality and rate gains not quantified.
Charbone: going concern material uncertainty disclosed in its 2025 MD&A; C$1.5 million cash at September 30, 2026; convertible loan facility carries dilution risk.
These are speculative investments carrying significant risk including potential total loss of capital. Coverage on aktiego.com is provided for informational and educational purposes only. aktiego.com is not a registered investment advisor. Nothing in this article constitutes financial, investment, or professional advice. Readers are encouraged to conduct their own due diligence and consult a qualified financial advisor before making any investment decisions. For more information please see our full DISCLAIMER.